Texas Eastern Transmission, LP submitted an application to modify its previous plans for the Entriken Compressor Station as part of the Entriken Amendment Project. Originally approved to install an electric-motor driven compressor, Texas Eastern now intends to use a gas-driven compressor instead due to concerns about securing adequate electrical power. The Federal Energy Regulatory Commission (FERC) plans to prepare an environmental assessment for this amendment, with the document expected to be issued by March 7, 2025. The deadline for federal authorization decisions concerning this project is set for June 5, 2025.
Simple Explanation
Texas Eastern Transmission wanted to use an electric plug to make a big machine work, but now they want to use gas instead because they aren't sure they can find enough electricity. The people in charge are checking to make sure this is okay and will say what they think in a report coming out soon.