Ohio Power and Light, LLC has filed a major original license application with the Federal Energy Regulatory Commission (FERC) for a hydroelectric project at the Robert C. Byrd Locks and Dam on the Ohio River in West Virginia. The project would involve constructing powerhouses, intake and tailrace channels, and a transmission line, with the goal of generating approximately 165,169 megawatt-hours annually. The public can view the application on FERC's website and request additional studies or agency status by March 24, 2025. The project is currently not ready for environmental analysis.
Simple Explanation
Ohio Power and Light wants to build a big machine in the river to make electricity, and they've asked for permission to do it. People can look at their request online and say if they think more information is needed before March 24, 2025.