Search Results for citation:"86 FR 9331"

Found 1 results
Skip to main content

Search Results: citation:"86 FR 9331"

  • Type:Notice
    Citation:86 FR 9331
    Reading Time:about 3 minutes

    Columbia Gas Transmission, LLC is asking for more time to finish their Line SM-116 Forced Relocation Project in West Virginia, extending the deadline to October 31, 2021. They have experienced construction delays due to rain and safety concerns, as well as impacts from the COVID-19 pandemic. The Federal Energy Regulatory Commission (FERC) is giving people until February 23, 2021, to comment on this request, and FERC encourages submitting comments electronically. If there are no disputes over the request, FERC will likely grant the extension without further formalities.

    Simple Explanation

    Columbia Gas needs more time to finish fixing some pipes in West Virginia because of rain and COVID-19, and they want until the end of October to do it. People can say if they agree or disagree with this by February 23, and if no one disagrees, the extension will likely be given.